Hello all,
I am hoping to have some elements clarified as it related to lead time calculation and MRP for IFS Purchased Parts.
On the inventory part record, the Purchasing Lead Time is calculated using the Calculate Purchase Leadtime, which takes several elements into consideration (supplier manufacturing lead time, external transport lead time, internal transport lead time, and internal inspection lead time). If this is not run, the field is blank, or a value can be entered. This seems to indicate the MRP uses the value in here for POR planning?
Would this then mean that the Supplier Manufacturing Lead Time on the SFPP is not used for MRP? If the Purchasing Lead Time is left at 0 or no value is entered, would MRP default to using the SFPP leadtime?
In this example, the PLT is set to 0 and SFPP record is set to 15 days. When MRP runs, would it default to 15 days even if there was a transport leadtime of 2 days?