Hello, we just went live with Apps10 and MRP is calculating Purchase Lead Time in Manufacturing Days (Monday-Friday schedule). We expect it to run using calendar days (7 day calendar). There are no supplier calendars set up and the help indicates, “If no value is entered in the field, an all day calendar will be used.“
I am confident it is a setting that needs changed, but I can’t seem to find it. Any help is appreciated.
Also, we are using Safety Stock to drive demand. Sorry for the vague description, but I feel like there is a simple solution.