Having an issue with Planning method A - for purchased finished good.
Using MS Level 1 - but if I set Min/Max/Multiple lot sizes to anything other than zero, Purchase req’s go away and get MS Supply lines instead. Also, I am using planning time fence as a surrogate for purchasing lead time, which doesn’t seem to have any functionality.
How do you specify whether MS1 or MRP is doing the planning?
This is all in IFS 8 (upgrading to IFS 9 soon I believe).