As per the current setup, when there is a part demand added in the system, the MRP calculates back from the requirement date and the purchase lead time for the part, and creates the purchase requisition on this day.
While this is regular practice, we need to be able to add an “offset” so that the MRP creates those requisitions earlier, and the parts can be delivered earlier for the relevant execution teams to have time to evaluate readiness and prepare accordingly.
Is there a field where such an offset can be added across all parts?
We rather not change the individual lead times since this would muddy the data hygiene and not align with actual supplier lead times. Not to mention the subsequent requirement to continue butchering future parts’ lead times.