Skip to main content

Hi

 

We have a question would appreciate any help!

 

A sales order is released and at planned stage, when we run MRP generates a requisition list of all stock items (not this order all options) note no stock is booked in yet as test system had cut over.

But when we released order to manufacturing order status at released and update MRP the requisition list is updated and reduces to just that requirement.

Why is this to help in understating using MRP?

Thanks

Laura

 

 

Just to clarify on this we are using heavily configured orders. 

These orders are also intersite transactions, so a retail site will release an order on the manufacturing site, where is sits at planned state in manufacturing until released.

We were looking at not releasing orders immediately at manufacturing, to allow changes post retail site release, which would then update in the manufacturing order through intersite.

Many Thanks,

Nigel

 


Reply