Missing date on PO Change Order

  • Jan 3, 2023 10:40 PM UTC
  • 1 reply
  • 68 views

Forum|alt.badge.img+8

Hi, we have PO change orders (POCOs) set as optional on our sites.  However, when one is created, all changes must be done through a change order, including dates.  They occasionally need to edit the planned delivery date on the POCO screen but it does not appear there.  Have any additional dates been added to the POCO screen in IFS cloud or are there plans to add it?

Thanks.

Best answer by RigsIrosh

It is only the Planned Receipt Date can be changed in the POCO lines even in IFS Cloud.

I guess the Planned Receipt Date is what is expected from the demand side and other dates like Planned Arrival and Delivery Dates are back calculated once the change is merged to the PO lines? 

But there could be different business scenarios.

 

View original

1 reply

Forum|alt.badge.img+8
  • Hero (Partner)
  • Answer
  • Jan 10, 2023 8:45 PM UTC

It is only the Planned Receipt Date can be changed in the POCO lines even in IFS Cloud.

I guess the Planned Receipt Date is what is expected from the demand side and other dates like Planned Arrival and Delivery Dates are back calculated once the change is merged to the PO lines? 

But there could be different business scenarios.