In our site, we have one part number, for which we use Inventory Part Planning Manuf/Acquired split (50%/50%)
What of course means that 50% of supply is purchased and another 50% is produced
But there is one problem with that parts with Lead Times Differences
Of course, Purchasing Lead time is far ahead of manufacturing lead time.
It entails the thing that we are releasing purchase order much earlier than prodution order
And lets say we have a demand for the date X for 200 pcs. Because of the split 100 of them has purchase requisiton and another 100 has shop order requisition
When the Purchase requisiton is released and SO req isn't then there is 100 covered by PO and 100 uncovered.
After next MRP this uncovered 100 pcs is again netted and calculated with the 50% split
So on next day we have a 100 PO released. 50 pcs po req and 50 pcs SO req. In total it gives us split of 75% vs 25% instead of desired 50/50
Do you believe is there any way to avoid that, and keep orginal values for SO and PO req without creating a SO with due date so far away ?
I tried prodution schedule but as i saw in simul environment, these are not visible in inventory part avaialbility planning
We also need to keep in mind that there are frequent changes in customer forecast which impacts planning of this part. So with every change we will need to readjust everyone once released shop order.
If this would be indispensable, then i tought about using MRP action proposal per planner to do so but maybe some of you have better ideas
So, please let me know if you have gone throught something similar to this already
Add
Ive also been introduced to idea of creating new Top part which consist 0,5 of Manuf product and 0,5 of purchase product. That would solve may of our problems but this is gonna be big workaround not utlising IFS possibilities.
Moreover to won’t let us to track where the Manuf/Purch parts were send. Now, we can do that through Lot Batch Trachking