Is there an impact from “Departure Route” on the calculation of earliest unlimited supply date on a part purchased from an internal supplier?

If yes, to which lead time (external transport lead time/transport lead time/internal transport lead time) does it affect?
Appreciate if someone can also share any help documents related to this functionality.

 

Thanks

 

Hi Malsha,

As I remember, when calculating the Earliest Unlimited Supply Date, which will take all the lead time parameters and their respective calendars into consideration for the primary supplier.

The ‘Supplier manufacturing lead time’ (Supplier calendar), ‘External transport lead time’ (External transport calendar- in ship via) and ‘Internal transport lead time’ (Distribution Calendar- in site).

You can find more information click the below link,

http://docweb.corpnet.ifsworld.com/ifsdoc/Apps10/Documentation/en/Purch/dlgCalcEarliestSupplyDate.htm

But I can’t remember any route engaged with this calculation, so better for you to check it with technical assistance.

Best Regards,

Indika