Hi, since my customer is Assembly-to-order,

their Master Schedule end-item is NOT finished-goods, but Unit(Component).

 

For some common components, it does belong to diffent blow-through parts.

 

But when I tried,  

seems IFS do NOT allow one end-item  belong to multiple blow-through-parts.

(the “Part-C” in the attached picture)

Is there any workaround for it?

 

 

 

 

 

 

Hi @Shou ,

 

As you have noticed, by design it is for finished goods (SKUs) and for components planning there is MRP.

Just thinking out loud here. How about master scheduling at Unit level (Unit-A and Unit-B) and plan components using MRP ?