Hi,
We have started to use the service and maintenance section of the system to record internal work done on our manufacturing tools. However whilst investigating moving this to the production of our new tools I have noticed an issue. When you pre post the work order to what we have classed as the project code (code F) I can not add departments to any pre posting on requisitions header that I raise. I have to go into every line on the requisition to add the department. Is this how the system is supposed to work? Or have I not set the permission up correctly to allow this?