Question, is there a way to include these two dates in the P.O. C.O. process (as part of the enforce rule)? Testing indicates these two are not included. Changing (only) the Promised Del. Date using the RMB context menu “Confirm with Differences via Change Order” does not invoke the P.O. C.O. process.
WHY I ask: We would like to capture these “Vendor Driven” date changes, holding the P.O. C.O. from Release (that’s a security issue-easy) until production schedules and commitments are considered by the materials planner.
Cheers!