Hi,
In the planning the cost amount is a calculated column from the saved quantity and unit cost.
On the transaction the unit cost is a calculated column from the saved quantity and cost amount.
The cost retrieval from things like Resources, material, purchase parts, etc. is always per unit, so that is then also applied to planning manual Expense and External planning.
Then for the reporting the cost amount is calculated, rounded according to accounting currency, and saved on the transaction and used for accounting, so this is the actual amount used in GL.
/Hans
Hi,
In the planning the cost amount is a calculated column from the saved quantity and unit cost.
On the transaction the unit cost is a calculated column from the saved quantity and cost amount.
The cost retrieval from things like Resources, material, purchase parts, etc. is always per unit, so that is then also applied to planning manual Expense and External planning.
Then for the reporting the cost amount is calculated, rounded according to accounting currency, and saved on the transaction and used for accounting, so this is the actual amount used in GL.
/Hans
Hi, Thanks for your time and explanation. Is it possible to set the Report manual transaction to consider per unit, not accounting currency? or another workaround to fix it? or is there any parameter in account currency that I can modify this?
Br.
Lopes