Question

Work Order Priority

  • 30 March 2023
  • 1 reply
  • 46 views

Userlevel 2
Badge +2

Hi IFS Guru,

I am looking for the insight, about Priority field in Fault Report, if I will select the Priority e.g. within 1 Week, will system give the Latest Start Date and Latest Finish Start, I need this, once I will select the priority, system should give the LAFD (Last Allowable Finish Date), which is fundamental to our business process applicable for Corrective Maintenance Work Order generated through Fault Report.

 

Regards

 

Shehzad  

 


1 reply

Userlevel 5
Badge +12

Hi,

Out of the box there is no relations between Priority and Latest Start Date and Latest Finish Date.

The priority is a user defined basic data and there is no place to put logic in to control the start and finish dates.

To achieve this you could perhaps create a custom event that based on priority values gives a latest start based on sysdate and number of days related to the given priority (could be that you need to create custom field in the priority basic data to store the number of days needed to calculate the latest start).

Reply