Solved

Work Centre Load - Planned Work Orders

  • 1 September 2020
  • 1 reply
  • 365 views

Userlevel 3
Badge +7

Hi All, 

 

I am planning a work order on an equipment object with an associated manufacturing work order.  My WO has an Obstructive Operation status and I am warned that the Work Task may interfere with planned Shop Orders.  I can see that the correct work centre is listed in the prepare tab.  I have shop order operations planned for the same time as the planned dates in the Work Order.   I cannot seem to see the planned load on the Work Centre where it shows that a Work Order is planned to be executed.  Is anyone able to point me in the right direction as to what I may be missing?

icon

Best answer by evrandree 10 September 2020, 15:00

View original

1 reply

Badge +2

Hi Chris. These are the requirements for the Work Task to show as Maintenance Load in Mfg Visual Planning and Mfg Visualizer:

Load from a maintenance work task. Note that below must be fulfilled to view maintenance load from this chart:

  • The task should be connected to an object which represents a work center resource.
  • The operational status type on the task should be Obstructive.
  • Planned start and finish date on the task has to be defined.
  • The task status should be Under PreparationPreparedReleased or Started.
  • The execution time (planned start/finish) needs to be defined on the task.

Reply