Hope someone can help. My customer is currently implementing IFS Cloud 22R2.
As we are migrating the historical data from the legacy system, we want to capture the due date on the calendar-based PM Action where the due date already passed. This is because not all equipment is being maintained on time and we need visibility on when it actually was due.
The problem I encountered that despite the Start Date on the Maintenance Trigger shows in the past (e.g., 01/01/2020) the Maintenance Plan generates the future date only. What we want is the Maintenance Plan to show the line for 01/01/2020 otherwise according to the Maintenance Plan this asset is only due in a couple of years, instead of being due for a while. I selected Valid From Date on the Work Task Template 01//01/2017 to ensure that all dates are valid but that doesn't seem to make a difference.