Skip to main content

hi,

its not possible to reopen several workorder at once. IFS allows to reopen one by one

how could it be possible to reopen several workorder at once ?

 

 

Hi,
Yes, this seems not possible.

Is it frequently done, like reopening several work orders at a time?

Regards,
Daniel

 


Hi,

The customer do it frequently because it is free and then change to become chargeable

Regards


Hi,

The customer do it frequently because it is free and then change to become chargeable

Regards

Sorry that I'm a bit slow, but what does that mean in the context of historical work orders?


Hi 

The customer finish the workorder but want to reopen it because he forgot to enter some information . My customer have one work task per workorder he would like to repoen worktask automatically when it reopen the workorder. That not possible.

 


That sounds like something a custom event can do for you.


Hi Matias

Thanks for your answer

I have an other issue about document attached to a workorder

To detach a document from workorder , i need to have admin right to the document ? 
with Edit Right is not possible ! 
 

but with a document attached to a Part. I can detach it even if i have edit acces only

Do you have an explanation ? how to allow a user with edit acces to detach a document from a workorder ?

 

Thanks Regards 


it is a permission issue. I’ve just allowed the user to delete connection and it works

Regards


Reply