Skip to main content

Hi,

I hope someone can provide guidance on the following: 

We are looking to streamline our PM actions and implement a form of  suppression to prevent work orders from being raised when the service year is not applicable. Specifically, we have equipment objects that require servicing at 1,3 and 5 -year intervals. 

 

Our goal is to create a PM action that raises work orders according to these intervals, while ensuring following: 

  • The 1 year PM action needs to raise a work order in year 1, 2 and 4 only
  • The 3 year PM action needs to raise a work order in year 3 only
  • The 5 year PM action needs to raise a work order in year 5 only

Is it possible to achieve this using standard IFS functionality, or would a CRIM be necessary? 

Thank you in advance for your assistance. 

 

 

 

Hi @DFSNYANDED , did you check the replacement functionality on the PM Actions?

In your exaple, 5 year PM Actio should replace both the 3 and 1 year PM Action

Then the 3 year should replace the 1 year PM Action

 

So it looks like this is standrad functionality:

 


Hi, you should be able to solve it with the “replaced by” function. The 1 year PM is replaced by the 3 and 5 year when they occur. You’ll find the replacement function on the PM. (It does not work if the PM actions are in a PM-structure though. I.e. the PM action are connected to another PM in a structure.)


Thank you @johan.orn & @EqeRobertK, we will give this a try 


Reply