Skip to main content

I am wondering why sometimes the Planned Start Date  in V10 shows up in the Maintenance Plan and sometimes it doesn’t. 

I was thinking it must be a simple click somewhere, or a field doesn’t always have a value.

Any help would be greatly appreciated.

Thanks,

@Huffman Please check if you have added a worklist line. Once the work list line is added, planned start and planned finish get calculated on the maintenance plan. Work list line becomes the task on the Work Order later.


@Dilini Arandara  Thanks so much, greatly appreciated.

 

 


@Huffman Glad to help :slight_smile: