Hello everyone,

I'm currently working on a configuration in IFS and need some clarity on how the system handles certain scenarios involving multiple PM triggers. Specifically, I have the following setup:

Calendar is set to Date Based Yes
Two or more Accumulated triggers set to Value Based Yes
A Limit parameter is also configured
My questions are:

If a Work Order is triggered by the Limit parameter, what will be the impact on the Accumulated triggers?

Will they reset, adjust, or continue independently based on their own settings?
How does the system handle the interaction between the Calendar trigger and the Accumulated triggers when both are set as described above?

What should I expect in terms of the scheduling and generation of Work Orders?
If anyone has experience or insights into this type of configuration, I would appreciate your guidance or any examples you can share.

Thank you in advance!

If Performed Date Based and Performed Value Based both are set then only one work order can exist. 


Once a work order is generated (even triggered by Limit parameter), existing Maintenance Triggers or maintenance plan is not changed. But no more work orders are created until the already generated work order(all work tasks from this PM) is set to work done.


Once the last work task of that PM is completed then all maintenance plans(calendar based/condition-Accumulated based) will be regenerated based on last work task completion date/last measurement at maintenance. No change in limit condition maintenance plan line. 

Hope this helps.