Link work tasks without dependencies on status

  • 8 February 2024
  • 0 replies
  • 39 views

Badge

Is there functionality to link work tasks under the same work order without dependencies on status (In IFS Cloud)?

We have several scanarios where we want to link work tasks, but the dependency types in “Work Task Dependencies” can not be used and/or we want to create IFS workflow to update status on some work tasks

Example, it should not be possible to set a QA work task to state Finished/Reported until all connected fault reports has status “Work Done”. “Reported to work done” is not a dependency type, but we could create a check in workflow if we had a connection.

We also have cases where the rule is that one task should not start until the other is started, but some times we need to do exeptions. The “Ignore Dependencie in Execution” checkbox could probably have solved this, but we can not see any affect on the status when changing the checkbox to true.