It is possible to pre-impute a cost center on a resource tools/equipement ?

  • December 13, 2021
  • 2 replies
  • 65 views

Forum|alt.badge.img+4

Hello !

I can’t find a way to pre-impute a cost center on a tools/equipement resource, do you have ideas to do so or it is impossible ? On the picture, i don’t find the field in the tools/eq screen 

 

 

Thank you,

Best regards,

Paul Bobet.

This topic has been closed for replies.

2 replies

Mayura Wasantha
Superhero (Employee)
Forum|alt.badge.img+19
  • Superhero (Employee)
  • December 13, 2021

/You are right. There is no way to predefine a Cost Center on the Tool/Equipment. May I know the business requirement here.


Forum|alt.badge.img+4
  • Author
  • Sidekick (Partner)
  • December 13, 2021

Thank you for your quick answer, we need it to preimpute the WO when doing a maintenance operation on the tool/equipement. But we can preimpute directly on the WO so we can do this for tool/eq. It was just to know if we could gain some time !