Hi All!

Few weeks ago, I couldn’t generate the WO of next line of PM if the status of the actual work task in “not completed”. Today I discover on Aurena V10 (UPD16 version) that I can generate all of the WO one by one without any restriction.

Is that a new IFS rule on this object?

Thank to all your advices

Hi,

 

I assume, you had this performed date base value set to Yes before. So, the system will not allow to generate a new WO, if the previous WO is not done. Please refer the field description shown in the image for this field.

 

Thanks,

Dilini