Hi,
Maintenance Planners usually make changes for the work order schedule after executing the automatic scheduling in Maintenance Planning Board (MPB).
Eg: Planner changes the planned start date of the work task by manually dragging and dropping the Work Task to a future date.
Is there an option in the MPB to reverse/undo the above change without manually dragging and dropping it to the date where it was earlier?
Thank you.