I cannot seem to create a PM that automatically generates a work order based on dates. Can you assist?
Best answer by Thilini Kumarasinghe
View originalI cannot seem to create a PM that automatically generates a work order based on dates. Can you assist?
Best answer by Thilini Kumarasinghe
View originalHello, I found this helpful but after following the steps I am still not seeing the extended dates on the Maintenance Plan. When I try to run the Calendar Generation I get an Error Message - There are no valid actions for the entered criteria.
PM is active
Maintenance Plan - start value is 1/8/2017 and Valid From 12/1/2016
The last Maintenance Plan was generated 6/12/20.
I believe it may be an issue with Calendar but I can not locate.
PM_PLAN_HORIZON is 2022
Maintenance Calendar out 2023
I have a scheduled Database Task - PM Generate Calendar is scheduled daily.
Any help will be much appreciated.
Thank you all. It was a combination of all of your tips that help me resolve the problem! Thank you so much!
If you have the pm actions then it might be that you are missing the scheduled database task running the calendar grneration feature.