We need to update a Time Report that has been transferred with the incorrect Hours.

 

How can we correct? we cannot remove from Work Task as we get an error 

How can we reverse the transfer and correct the Task Transaction?

Hi,

 

You can negate the incorrect time reporting, by adding a minus value of the originally reported hours,  and then adding the correct time reporting hours.

 

 


Perfect! That is exactly what I needed :) 


@lisa.gilesAB ,

You can also delete the wrong time reporting, by deleting the respective transactions from work task transaction. 

Regards,

Mithun K V


Hi @EqeMithuV in Reported status of the Transaction, yes you can delete. But, In transferred status, deleting is not possible. That is why the error that shown above is coming.