Hi All,

 

Customer has Upgraded to UPD12 recently and they have faced to permission issue when assigning resources to the work task demands(screenshot is attached below). After our investigations found that user didn’t have permissions to MAINT_RESOURCES_LOV6. That is separately added from UPD12. However we like know as to why it has an additional LOV added with permission sets?

 

 

Best Regards,

Nipun

Best answer by Janitha Jinarajadasa

Hi @Nipun Gunaratne ,

 

From Bug Id 157533 [ Please check the bug description for more details] released in UPD11, the view MAINT_RESOURCES_LOV6 was introduced. The list of values for the Allocated_To field is fetched from this view.

This topic has been closed for replies.

1 reply

Forum|alt.badge.img+14

Hi @Nipun Gunaratne ,

 

From Bug Id 157533 [ Please check the bug description for more details] released in UPD11, the view MAINT_RESOURCES_LOV6 was introduced. The list of values for the Allocated_To field is fetched from this view.