HI Community,

Looking foreward for your advice on following,

 

  1. Create a transport task. 
  2. Go to the WaDaCo Warehouse Data Collection configuration page. 
  3. Release the PROCESS_TRANSPORT_TASK_PART for the company. 
  4. Start scanning and select the created transport task ID and proceed. 
  5. When the “To location” data item appears, go to the LOV. Notice that only the location which is mentioned in the created transport task is available in the LOV to select.  

 
Why the multiple locations are not available on the LOV to pick?  

As I remember its only the LOV that show the to location from the transport task, but you can manually outside the LOV change that by entering or scanning another location instead, the validation will allow it, if its a valid location.

Due to some technical reasons we kept the LOV to only show what was saved on the original transport task.


The LOV for “To Location” in WaDaCo “PROCESS_TRANSPORT_TASK_PART” process, is included only the To Location which is mentioned in the transport task. 
The user is allowed to enter a different location by scanning or entering the value manually. So, this gives the user the option to clearly see the To Location which was planned for a particular transport task while giving the option to enter a different location as well if there’s any requirement for that.

I think that’s the main reason for the system to be designed this way