We are in the process of rolling out WADACO. But have a requirement to manually issue parts (Mainly consumables, that aren’t called up in a BOM), as people come to stores and request certain items on the fly. 

 

We are using issue inventory part and pre-posting to cost centres which works well with WADACO, but there is also a requirement to issue certain items (Again mainly consumables) to a project as well. 

 

We were hoping to achieve the same thing by using issue inventory part, and pre-posting to a project, but this doesn’t seem possible as we get an error saying “External project must have a project activity connection” which seems to indicate that an activity is required, something that you can’t specify when using Issue Inventory Part. 

 

Has anyone found a way around this? We currently use Material Req’s or project misc demand, but there is no way to create either of these items using WADACO. 

Similar question here, but for Cloud.


I don’t know much about the functionality in this process or how it works in the regular client for similar flow, but in the code there is a comment that points that process Issue Inventory Part is not supporting projects.

“-- Issue inventory part doesn't have support for project”

I don’t know why or if this was scoped out as a limitation when it was built or the reasons for it.

 