Hi,
In our current flow, we move reserved parts from the stock to a pre-production location using WaDaCo. We take all reserved parts for a shop order, and combine them into a transport task to move them from the warehouse into the production area (but we don’t issue yet, just move).
However, we don’t have any logic in this.
The transport task is sorted using Source ref 1, which is the line number from the the Shop order.
But if we need part A from location AB01 for the first line, and the third line asks for this part again, the operator will first be directed to location AB01, for the second line to another location, and for the the third line again to location AB01.
Any idea how to optimise this?