Hi Everyone, I’ve been breaking my head with this one today. We have two sites, site 1 is the supplier for site 2 (customer). We do have multi-site planned checked on the supplier for purchase part on site 2 for this part number.I cannot figure out why my inventory goes negative on site 2 on 1/16, and a distribution order is created by MRP and scheduled to arrive until 1/20 - and not the day before ( 1/15) to satisfy demand. 😣 This is a screen shot from the Inventory Part Availability Planning (IPAP) screen: Any ideas how i can make the dist order to arrive before inventory goes negative? Thank you!