@Asterix probably you would need to describe a bit what you’re trying to get with this post. The wording of the topic is way too general .
You might find the answers in the Technical Documentation here:
https://docs.ifs.com/techdocs/23r1/
@Asterix, Marcel is right, this is a fairly broad question, but typical areas where I have seen assumptions include:
- Company commitment / project sponsorship
- Scope inclusions / exclusions
- Ability to adapt processes to standard IFS / keep the same
- Critical requirements to be addressed / handled another way
- CRIM items (customization, reports, interfaces, mods)
- Data cleansing and restructuring requirements
- Resource availability / constraints
- Competing demands for time / other projects
- Technology stability / changes expected
I hope this helps. Chris