Our business case requires reusable parts of the quantity of 1 to be used by more teams within the same day.

To demonstrate this scenario we have sent two CALL splittable activities with the duration of 4 hours both requiring the same part and one DEPOT activity. We have also filled up the depot with Part_Stock entity to the quantity of 1.

In the picture you can see that PSO allocated activities which overlap, despite the fact that there is only one unit of the part. Moreover, there are some DEPOT activities missing (we expect that for each load (part_usage=-1) of a part there is also an activity for getting the part back to the depot (part_usage=1))

Is such behaviour correct? If so, can you please suggest a different way to solve our problem?

Secondly, we would like to ask how can the circled activities be allocated to the second team who does not posses the part at that time.

Thank you