Hi Team,

I’m hoping to execute IPR without using forecast option which feed from Demand planner. Yet I face below error:

 


INVPLA module is installed in the system and there is no demand plan service. Do system admin needs to enable any other service to use IPR functionalities ?

Hi ​@Ashni Nayanthara Please check if this customer has a demand plan server configured

 

Please check the below setup in your server

<You may enable IPR or Forecast & IPR 

<Second thing please check whether data available in the Demand Planner Server window ,if not try to add data and Refresh the IPR

So you may get server up and running and data will refresh without any error

 


HI ​@AshenR ,

 

Thanks a lot for information but I really wonder whether we really need to have demand planner too since we can configure the planning hierarchy to use demand model : History


Hi ​@Ashni Nayanthara ,

Yes, the demand plan server needs to be configured as well.

Thanks,

Arosha