Hi,

In a customer contract you have 2 items as OOS.

These items have the same planning of MP, but for one of the items, we cannot run the preventive maintenance in the winter months (ski station).
If we set this line at seasonal in the contract (april to october for example), do we have an impact on the MP planning (no dates between november to march) ?

Thanks and Regards 

 

anthony

 

Hi Anthony,

To confirm the behaviour for you, I did the following. Created a one year contract with two objects of service.  One OOS was for the full year and the other covered only from April to August with the seasonal flag enabled on this OOS.

Ran the PM Batch Scheduler for just this contract to cover the contract months and the results were the first OOS had all the months scheduled while the second only had the seasonal months scheduled.

I believe this is what you were asking?

First OOS - all months scheduled
Second OOS - only the valid OOS months scheduled

Kind regards,

Phil


Hi @Phil Seifert 

Very helpful 

Thanks

 

anthony