Skip to main content

Hi,

 

Any Lead to advice on the test flow on creating a project transaction through forwards supplier invoice process.

 

Regards,

Hi @RASFE ,

You can follow the below step

  • Create a purchase order for a no part ( as a easy step)
  • Receive the purchase order
  • Create Manual Supplier Invoice
  • Match the invoice with the PO 
  • Do right mouse on manual supplier invoice and choose option Project Reporting ( This will re-direct you to forward supplier invoice screen
  • Now add the project & activities to which you need to distribute the invoice cost
  • enter the cost & report code and save
  • this will create project transaction for the respective activities & projects 

You can also create Supplier Invoice Margin ID and connect it to project such that the distribution cost will be automatically calculated based on the pre-defined % specified against the report code.

Hope this helps!!

Regards,

Mithun K V


Reply