Hi,
I have enabled Project Budget Control settings as below for the Project and setup the Project Budget Control consumption checkpoint as Create Purchase Requisition Line. When I created a project supply request that exceeding the budget it does not block creation of the Purchase Requisition.


But when I tried Create Purchase order line and Release Purchase order line as consumption check point this budget control option is working.
Is there any reason for this?