Question

Calendar Plan Lines does not work properly according to the specified year

  • 1 October 2019
  • 1 reply
  • 145 views

Userlevel 7
Badge +18
Expectation is to generate calendar plan until maintenance plan horizon. But for some cases it gets stopped

1 reply

Userlevel 5
Badge +8
This seems to be possible with the Calendar ID that you are using.

The App9 functionality of Calendar ID is deviated from previous version. Basically the maintenance plan will not create a line in case the it will fall into a date defined a non-working day from the calendar itself.

Calendar is optional and can be used to avoid that PM lines are created during certain calendar periods,
e.g. according to seasonal patterns.
This is to make sure no PM lines are created during a vacation period if production stand still during that period.

A calendar can be used in conjunction with the maintenance organization calendar which makes sure the PM lines are created on working days. But while the calendar of the maintenance organization will move lines outside working time forward to next coming working day, this calendar will make sure such lines are omitted from the maintenance plan

In App9 Calendar ID is not essential. Calendar ID is mainly use in a time where we want to limit the maintenance plan for certain time. If we use a calendar ID & the maintenance plan date associated to a leave date (defined with calendar) in such case the maintenance plan will not be generate afterwards. When you are using the 24 interval the date may have changing & allowing to generate maintenance plan forward till the date defined with maintenance plan horizon

Reply