Question

Project Deliverables - Supply Option not working?

  • 10 September 2021
  • 1 reply
  • 130 views

Userlevel 3
Badge +7

Hi All

 

I have created a project delvierable for which I want to source most of my products from standard stock. It looks if I change the supply option to MRP it should request this from standard inventory but when I raise the shop order for the top level, every line appears as project inventory. This is Apps10 UPD12.

 

Have I misunderstood the help, or am I missing a function?

THanks! 


1 reply

Userlevel 3
Badge +7

Answered my own question,. the engineering part was set incorrectly!

Reply