I am having a project deliverable structure as below.
[level 1]: material project deliverable item connected to a manufactured inventory part with MRP code A
[level 2] : non material project deliverable item connected to a manufactured inventory part with MRP code P (or K) and engineering phantom part with MPL part value "no demand"
[level 3] : material project deliverable item connected to a purchased inventory part
When I create the shop order for [level 1], the components are correctly fetched from the phantom parts but - again - the phantom part n° is not displayed on the shop order material line.
In this case, the phantom part exists as an inventory part, so why isn't it working?
Best answer by Peshala Fernando