Tie parallel operations to the main operation in APB

  • 18 June 2021
  • 1 reply
  • 76 views

Userlevel 5
Badge +12

If I have one main operation and others are parallel, is there a way that the parallel operations are tied to the main operation, so that drag the main operation will bring the parallel operations together, without leaving them behind?


This topic has been closed for comments

1 reply

Userlevel 2
Badge +7

For this case User can create an Operation block for set of parallel operations and then it is possible to move entire block to the needed slot in the production schedule.