I’m noticing an issue on Shop Floor workbench. Currently, we have a 1st and 2nd shift. Shop Orders may span multiple shifts and it appears that if an operator on a prior shift (1st) is clocked into Start Production, a 2nd shift employee cannot join that operation without creating a Team and joining that. Is this correct, or is there a way to allow individuals to Start Production on operations without having to use a Team? Thank you!

icon

Best answer by Björn Hultgren 5 August 2020, 17:12

View original

2 replies

Userlevel 7
Badge +23

Hi, 

 

It is possible for the 2nd operator to join the operation without using team reporting.

In Enterprise Explorer you click Modify Ongoing Operation button, the click the Join button inside that dialog box. 

In Aurena this process has been simplified, so there's a separate button for Join Setup, or Join Production directly. 

Userlevel 6
Badge +17

@Björn Hultgren That was it! Thank you very much!