Hi

using IFS apps 10 and have been playing around with the Resource structures and resource analysis to replicate actual resource constraints.

however there is an icon on the resource structure that I do not know the meaning to (below highlighted in red) can anyone help?

 

Also can anyone explain the difference 1) Schedule capacity, 2) Adjusted capacity and 3) utilization capacity on the resource analysis graph?

 

kind regards

Jamie 

icon

Best answer by MR10 23 September 2021, 12:16

View original

This topic has been closed for comments

1 reply

Userlevel 5
Badge +10

The Triangle indicates, as I can remember, that you have overplanned the resource at some point in time. (meaning the planned values exceed the available capacity)