Question

safety stock

  • 22 February 2021
  • 4 replies
  • 256 views

Userlevel 3
Badge +6

Hi – can anyone tell me if MRP will trigger purchase requisitions for status 5 parts that are showing inventory below safety stock?


This topic has been closed for comments

4 replies

Userlevel 2
Badge +7

I’m not sure what you meant by status 5 parts.

But yes MRP creates supplies (PRs for purchase parts) including the Safety Stock. If User needs to maintain the Safety stock from MRP run date User can enable the ‘Plan Safety Stock Receipt on MRP run date’ check in Perform MRP dialog. 

Userlevel 3
Badge +6

Hi Lakshan,

Thanks for your reply :)

Here we have Part status 5 means ‘Supply Hold Due to Pending Changes’.

Also, on which screen do we enable ‘Plan Safety Stock Receipt on MRP run date’ check in Perform MRP dialog. 

If possible can you attach snip.

 

Thanks again.

 

Vaishali

Userlevel 7
Badge +21

Hi @Vchandna ,

 

You would check the checkbox on the Perform Site MRP dialog box or if you are running a nightly background job you could check the checkbox on the Event Action.

 

Regards,

William Klotz

Userlevel 2
Badge +7

Hi Vaishali,

 

I think you already got the required snaps from above reply from @william.klotz reply above.

 

Thanks!