Hi all.
I’m trying to set a up a resource break but how can I change to schedule?
I already recalculated the resource, opened in MPB but it still let me schedule the resource during this time.
tks
Best answer by lopespetro
View originalHi all.
I’m trying to set a up a resource break but how can I change to schedule?
I already recalculated the resource, opened in MPB but it still let me schedule the resource during this time.
tks
Best answer by lopespetro
View originalGood job! Thanks for letting me know. I’ll delete the post for Dharshana...he’s a pretty busy guy.
Hi, I could get it.
I need to schedule the break inside MPB before schedule the work task.
Tks for attention!!