When a Calendar Generated PM Action generates a Work Order, how does IFS calculate the latest finish date?  What is the IFS logic?

icon

Best answer by anmise 9 November 2019, 09:43

View original

2 replies

Userlevel 7

When a Calendar Generated PM Action generates a Work Order, how does IFS calculate the latest finish date?  What is the IFS logic?

I believe all it does is take the last working day of the planned week in maintenance plan and sets it as the latest finish date. If you set a last finish date on the maintenance plan line manually, it will be set on the work order, but from my testing it doesn’t seem to transfer across to the work task itself. @JerryB any input here?